Xi'an Airport Phase III Lighting Station Relocation Project Successfully Concluded

At 4:00 AM on March 29, the final approach lighting circuit of Xi'an Airport's No.0 Lighting Station was successfully relocated, marking the triumphant completion of the most technically challenging and longest-duration airfield construction project during the Phase III expansion-the lighting station relocation and circuit modification initiative.

Xi'an Airport Phase III Lighting Station Relocation Project Successfully Concluded

As the final phase of the airfield lighting system upgrade, the No.0 Lighting Station project involved complex multi-circuit power supply modifications requiring execution without disrupting normal flight operations. The Lighting Station Party Branch of the Airfield Management Department formed a Communist Party Member Vanguard Team integrating "technical expertise, safety assurance, and emergency response," assigning responsibilities with military precision.

Since November 2021, the team conducted:

Dual-verification planning using "OviMap 3D modeling + simulated runway drills"

Contingency preparation with dozens of emergency scenarios rehearsed

Nighttime preparatory work including cable laying and equipment debugging during post-flight hours

The decisive battle occurred from March 22-29, when a specialized task force capitalized on daily 1:00-6:00 AM operational windows to:

Relocate 40 power circuits in batches

Achieve seamless system transition

Maintain strict "construct-inspect-restore within single night" protocols

The newly operational Phase III airfield lighting system features:

Modular design with industrial-grade reliability

Digital twin and AI self-diagnosis capabilities

Enhanced all-weather operational resilience

This advancement propels Xi'an Airport into "full-process digitalization and all-scenario intelligence" for airfield lighting management, accelerating its transformation into a "Four-Star Smart Airport."